As the weather warms up we are getting closer to our project’s substantial completion in December. As a result, I want to share some important milestone accomplishments for the Weston Tunnel Project that will be occurring this month! In preparation … Continue reading
Weston Road will be closed nightly for 8 hours between Oak Street and St. Phillips Road, between 10:00 p.m. to 6:00 a.m. the following morning. These closures will take place from Monday, January 6th to Friday, January 10th. These closures are necessary to safely relocate the existing Bell … Continue reading
Beginning August 12, GO will be ramping up concrete pour preparatory activities for the upcoming 18-hours continuous pours for the Weston tunnel base slabs. Work outside of these hours will occasionally be needed to build and remove forms. Details… … Continue reading
On Tuesday, July 2nd, Bell Canada will begin excavating and reconstructing a utility hole at the intersection of John Street and South Station Street. This work is expected to take 6 to 8 weeks. Click for road closure details… … Continue reading
On Sunday, July 7th, John Street will be closed to both pedestrians and vehicles at the corridor from 7 am until 7pm. Details… … Continue reading
GO Transit is pleased to announce that the Weston Community Office is now open to answer community questions and concerns about the Georgetown South Project. You are also invited to the Grand Opening of the office to be held on … Continue reading